Construction companies need working capital because they pay for materials, labor and equipment weeks before progress payments arrive — and part of every payment is often held back as retainage until the job is done. Pay-when-paid clauses and change-order disputes stretch the gap further, and sureties size your bonding capacity partly on working capital.

The cash gap on a commercial project

Subcontract on a commercial build (illustrative)

cash gap · 65 days
Day 0Day 180
  1. Day 0− Materials and equipment rental
  2. Day 14− Crew payroll (and every 2 weeks after)
  3. Day 30− Second payroll and overhead while the pay app is reviewed
  4. Day 65+ Progress payment, minus 10% retainage
  5. Day 180+ Retainage released after completion
Illustrative only. Retainage rates and payment timing are set by each contract and, on some public work, by statute.

Retainage in numbers (illustrative)

A $100,000 progress billing with 10% retainage

  • Work billed this period$100,000
  • Paid now (after retainage)$90,000
  • Held as retainage until completion$10,000
Across several open jobs, retainage alone can tie up a large share of a contractor's cash.

Why do contractors run short of cash?

Retainage

A slice of every payment held until the end of the job.

Progress billing cycles

Monthly pay apps, then approval and payment delays.

Pay-when-paid clauses

Subs wait until the GC is paid by the owner.

Materials up front

Long-lead items and price escalation.

Payroll and equipment

Crews and rentals billed weekly or biweekly.

Bonding capacity

Sureties weigh working capital when sizing bonds.

How much working capital does a contractor need?

Retainage is the number most contractors underestimate, because it is invisible in the monthly cash flow until the job ends.

Illustrative: $500,000 contract, 10% retainageAmount
Billed over the job$500,000
Held back as retainage$50,000
Releasedafter completion and final approval
Cash unavailable while you are still paying crews$50,000

Stack three jobs at that size and $150,000 is sitting in retainage while payroll, materials and equipment rental keep running. That is also why sureties ask for working capital: bonding capacity is a judgment about whether you can carry the gap between billing and collection, not just about your backlog.

Funding options for contractors

OptionFits which gapSpeedCostWatch out
Business line of creditPayroll and materials between pay appsDays–weeksLow–mediumCovenants tied to WIP
Construction invoice factoringApproved pay appsDaysMediumRetainage usually not advanced
Supplier credit / joint checksMaterialsImmediate once approvedLowLien waiver paperwork
Equipment financingMachines and vehiclesDaysLow–mediumCollateral
SBA 7(a) / CAPLines (contract)Contract-specific working capitalWeeks–monthsLowTime, documentation
Merchant cash advanceEmergency only1–3 daysHighDaily debits vs. 60-day pay cycles — see MCA default

Why banks often say no to contractors

Bank concernWhat helps
Lumpy, project-based revenueA current WIP schedule and backlog report
Underbilling and fadeJob-cost accounting reviewed by a construction CPA
Retainage and slow GCsAR aging by customer, with retainage shown separately
Bonding and claims historySurety letters and clean claims record

Carrying advances already? See MCA consolidation lenders or MCA debt restructuring.

Frequently asked questions

What are construction companies’ working capital needs?

Contractors fund materials, payroll and equipment for weeks before a progress payment arrives, and a portion of each payment — retainage — is often held until the project is complete. Pay-when-paid clauses can push subcontractor payments back further.

What is retainage in construction?

Retainage is a percentage of each progress payment that the owner or general contractor withholds until the work is finished and accepted. It is commonly around 5–10%, set by the contract and, on some public projects, by law.

How do I calculate WIP in construction?

A work-in-progress (WIP) schedule compares, for each job, the costs incurred and estimated percentage complete with what you have billed. Billing more than the work completed is overbilling; billing less is underbilling, which ties up your cash. Lenders and sureties review WIP schedules closely.

Why does working capital matter for bonding?

Surety companies look at a contractor’s working capital and net worth when setting bonding capacity. Stronger working capital usually supports larger bonded projects.